Prospect Park Capital Improvement: Lakeshore Restoration

Organizations: Prospect Park Alliance

Summary Description: This capital project funds environmental and accessibility improvements along the shoreline of the Prospect Park Lake

Status: In progress - Design Phase

Expected Date of Completion: Estimated phase 2 completion: 2028-2029

Project Website: https://www.prospectpark.org/learn-more/what-we-do/advancing-the-park/capital-projects-tracker/


Summary

The Lake at Prospect Park offers excellent recreational and scenic opportunities to park goers from Brooklyn and beyond. Prospect Park Alliance, the non-profit organization that sustains the park in partnership with the City, undertakes a variety of restoration and improvement projects throughout the park. This $20 million, multi-year project will include environmental and accessibility improvements to ensure the lakeshore is accessible and sustainable for future generations. These investments will restore the waterfront from just south of Lakeside to the Peninsula, restore lake edge and 3 of its island to improve wildlife habitats and nesting areas, and transform the vehicular Wellhouse Drive into landscaped bike and pedestrian paths, adding roughly 2 acres of additional green space to the park.

The Prospect Park Alliance encourages residents to submit a Letter of Support for additional funding from the City Council. Learn more.

Timeline

2028-2029
Estimated Phase 2 Construction

2028-2029
2027-2028
Estimated Phase 1 Construction

2027-2028
2026
Estimate Design Completion

2026
March 6, 2024
Lakeshore Restoration Virtual Meeting

March 6, 2024
March 2024
Brooklyn Borough Board Approval

March 2024
February 16, 2023
Lakeshore Restoration Virtual Public Meeting

February 16, 2023
November 21, 2022
Prospect Park Lakeshore Restoration Public Meeting held by Prospect Park Alliance

November 21, 2022
July 2022
NYC budget allocates $2 million toward restoration, matched by a $1 million allocation by the Mayor

See the FY2023 budget presentation to City Council

July 2022
June 22, 2022
CB14 Community Environment, Cultural Affairs & Economic Development Committee meeting

CB14 hosted a community conversation with Christian Zimmerman, Vice President, Capital & Landscape Management, Prospect Park Alliance, regarding the Lakeshore Project. Watch Meeting

June 22, 2022

Documents

June 22, 2022 CB14 Community Conversation about the Lakeshore Restoration Project – Recording
FY23 Budget Presentation about the Prospect Park Lakeshore Project
Scroll to Top